Yorba Linda Spur Construction Advertisement

County of Orange
Orange County Public Works (OCPW)
Flood Control Division
As of: 1-26-11

Orange County FCD Projects Advertised for Construction

Bid Documents are only available by mail or to pick up at OC Public Works Central Files located at:

Development Processing Center Cashier
300 N. Flower St, 1st Floor 
Santa Ana, CA 92703-4048 

7:30 AM to 4:00 PM
Monday through Friday

Questions concerning the purchase of Plans and Special Provisions and obtaining a copy of the plan holder's list should be addressed to the Cashier, County of Orange, OC Public Works/Central Files Staff 714-667-9780.

Santa Ana River Interceptor (SARI) relocation Yorba Linda Spur Procject within facility E01 and the Santa Ana River Trail from the SAVI Ranch Development to the Green River Golf Club Bid Opening Date: March 9, 2011 at 2:00 P.M. Advertising Starts: January 26, 2011 Engineer's Estimate: $7.3 Million (does not include contingency) Construction Duration: 200 Working Days

Pre-Bid Meeting

A pre-bid meeting was held on Thursday, February 3, 2011, at 10:00 a.m. at the Green River Golf Club clubhouse located at 5215 Green River Road, Corona, CA, 92880. Attendance at the pre-bid meeting was highly recommended for all contractors bidding the PROJECT. The pre-bid meeting allowed prospective bidders an opportunity to visit the PROJECT site, discuss the PROJECT and receive clarification of the Bid Package. Questions regarding interpretation of the Bid Package were not answered at the meeting, but will be addressed thereafter via issuance of a formal written bulletin. Subcontractors, material suppliers and vendors were encouraged to attend.

Bulletins/Addenda

Bulletin No. 1
Bulletin No. 2
Bulletin No. 3

Bid Package

Volume 1: Special Provisions
Volume 2: Reduced Size Plans
Volume 3: Geotechnical Data Report
Volume 4: Geotechnical Baseline Report

Reference Reports

  1. Geotechnical Interpretive Report
  2. Water Quality Management Plan
  3. Habitat Management and Monitoring Plan
  4. Pipeline Inspection Report (CCTV Inspection for 18” VCP Sewer at La Palma Ave.)
  5. Planholders List

Bid Information

Sealed bid proposals from Contractors can be sent to the following address:

Bid Proposal for Santa Ana River Interceptor Relocation: Yorba Linda Spur
Office of the Clerk of the Board of Supervisors
Room 101, Hall of Administration
County of Orange
333 West Santa Ana Blvd.
Santa Ana, CA 92703

Submit bid proposals to the above address on or before Wednesday, March 9, 2011 at 2:00 p.m. at which time they will be publicly opened and read in Room 169, 1st Floor, of the above address.


CEQA Certification and Addendum Approval Dates

October 6, 2009 and October 20, 2010