Project Updates and Schedule

In addition to the Santa Ana River Interceptor (SARI) Relocation Project schedule, monthly updates will be posted here to keep you apprised of our progress and any upcoming critical dates.

Current Schedule *

Yorba Linda Spur

  • Advertise for Bids: Jan. 26 – March 9, 2011
  • Pre-Bid Meeting: Feb. 3, 2011
  • Bid Opening: March 9, 2011

SARI Mainline (Including Metering Station)

  • Advertise for Bids: March 2 – May 11, 2011
  • Pre-Bid Meeting: March 17, 2011
  • Job Site Tours: March 23 & 24, 2011
  • Bid Opening: May 11, 2011

*Construction Contract has been awarded