Goldenwest St. to Gothard Ave.

OCFCD Facility No. C05/06
1150-ft upstream Goldenwest St. to 1150-ft upstream Gothard Ave. including Murdy Channel and the confluence with Oceanview Channel

Location: Huntington Beach

District: Supervisorial District 2


Project Information

East Garden Grove - Wintersberg Channel (Goldenwest St. to Gothard Ave.)

This channel project converted a reach of earthen trapezoidal channel only capable of conveying runoff from storms with a recurrence magnitude of 10-years or less to a full 100-year conveyance facility. This project is one of several phases of an overall C05/C06 Improvement Program, and not until all the phases of this channel system are complete, will a level of protection from the 100-year storm event be provided to the adjoining community and watershed.

The channel is now 60-feet wide by 16-feet high. The project length was approximately 1900 linear feet, upstream of Goldenwest Street and downstream of Beach Boulevard within the City of Huntington Beach.


C05 Map
View PDF


Start Date: 04/2001

Completed Date: 08/2001


Quantities